Ibadan

Felele Idi Odo Junction–Splash FM Radio Station–Onigari Felele Expressway taken on 12 February 2025

Ongoing Reconstruction of Felele Idi Odo Junction–Splash FM Radio Station–Onigari Felele Expressway (3.5 km)

An update and pictures of the ongoing reconstruction of Felele Idi Odo Junction–Splash FM Radio Station–Onigari Felele Expressway, Ibadan, Oyo State. The 3.5 km Felele–Idi Odo Junction–Splash FM–Onigari Expressway is undergoing a long-overdue rehabilitation. Though… Read More »Ongoing Reconstruction of Felele Idi Odo Junction–Splash FM Radio Station–Onigari Felele Expressway (3.5 km)

Rehabilitation of Iwo Road Roundabout and expansion of the Scope of the Ongoing Reconstruction of the Adegbayi Junction-Bus Terminal-Iwo Road Interchange, taken on 4 February 2025

New Project: Rehabilitation of Iwo Road Roundabout and Expansion of the Scope of the Ongoing Reconstruction of the Adegbayi Junction-Bus Terminal-Iwo Road Interchange

This is an update and pictures of a new project: the rehabilitation of the Iwo Road Roundabout and the expansion of the scope of the ongoing reconstruction of the Adegbayi Junction-Bus Terminal-Iwo Road Interchange. The… Read More »New Project: Rehabilitation of Iwo Road Roundabout and Expansion of the Scope of the Ongoing Reconstruction of the Adegbayi Junction-Bus Terminal-Iwo Road Interchange

The reconstruction of the 15.53 km UI-Bodija Market-Secretariat-Total Garden-Beere Roundabout Road taken on 21 January 2025

Ongoing Project: Reconstruction of UI-Bodija Market-Secretariat-Total Garden-Beere Roundabout Road (15.53 km)

An update and pictures of the ongoing reconstruction of the 15.53 km UI (Preboye Junction)-Bodija Market-Secretariat-Total Garden-Beere Roundabout Road. Recall that the UI-Bodija Market-Secretariat-Total Garden-Beere Roundabout Road was approved under Lot 1 of 10 roads by the… Read More »Ongoing Project: Reconstruction of UI-Bodija Market-Secretariat-Total Garden-Beere Roundabout Road (15.53 km)

The rehabilitation of some selected roads within Old and New Bodija, taken on 20 January 2025

Ongoing Rehabilitation of Selected Roads within Old and New Bodija, lbadan Metropolis (7.172 km) and the State Secretariat

The rehabilitation of selected roads within Old and New Bodija in the Ibadan Metropolis (7.172 km) is in full swing. The roads being rehabilitated include roads affected by the Bodija Explosion, which occurred on 16… Read More »Ongoing Rehabilitation of Selected Roads within Old and New Bodija, lbadan Metropolis (7.172 km) and the State Secretariat